10 TPD Mash Feed Production Line in Kazakhstan

10 TPD automatic batching mash feed production line installed at the project site in Kazakhstan
Site layout and scale of the mash feed production line inside the plant

A 10 TPD mash feed production line with automatic batching was commissioned in Kazakhstan across 22 working days in January 2026, drawing on a wheat-based raw material. The line combines a 160/200 kW hammer mill, a 1-tonne batching scale, a 15 kW single-shaft ribbon mixer and a 278.2 kW installed drive base, and it was handed over with operator training and operation manuals in two languages. This report sets out why a line of this size is worth building in-house, what it had to work with on site, and what the commissioning record actually shows.

FeatureDetail
Project type10 TPD automatic batching mash feed production line
LocationKazakhstan
Design capacity10 TPD
Raw material basisWheat as the main component; barley held in reserve
Process stagesIntake, grinding, sifting, batching and mixing, packing
Installed drive power278.2 kW
Batching accuracyStatic ≤1‰, dynamic ≤3‰; mixing uniformity 97.7%
On-site commissioning8–29 January 2026, 22 working days

Why Build an In-House Mash Feed Production Line Instead of Buying Compound Feed

The case for an in-house mash feed production line is not whether the machinery can perform its tasks exceptionally well, but rather a matter of cost and who holds control. In this 10 TPD mash feed processing line, operation buys raw material instead of finished feed, and holds the formula itself.

Cost Structure: What an In-House Line Changes

  • What Stops Being Paid For: A purchased bag of feed carries the seller’s raw material cost, processing cost, margin and freight. An in-house line removes the finished-feed margin from the calculation and converts the input into raw material plus processing.
  • Where the Floor Sits: The floor under that calculation is set by the scope split. On this project the interface between supply and self-build was defined in the equipment list: piping, platforms, ladders, handrails, stair treads and the main cable from the switch room to the motor control centre were explicitly on the site side, while the process equipment and the control system came from the supplier. Understanding that line before signing is what separates a workable budget from a surprise.

Formula Control and Batch-to-Batch Consistency

  • The Formula Replaces the Supplier’s Decision: An automatic batching control system with a recipe manager puts the formula in the hands of the operation. The batching controller on this line runs on a Siemens PLC with a touchscreen interface and a stored recipe library, so a formula is a saved set of parameters rather than an instruction passed down the chain.
  • What Consistency Actually Requires: Consistent output requires two things that bought feed cannot guarantee: that each ingredient enters at the intended weight, and that the mixed batch leaves the mixer homogeneous. Both are engineering quantities on this line, and both are verified on site rather than assumed.

Preconditions: Site, Power, Labour and Raw Material Supply

  • Four Gates Before the Line Runs: Four conditions decide whether a line of this size is worth installing. Site: whether there is a place to receive, store and move raw material through the intake. Power: whether the supply can carry the installed load and the starting current of the largest motor. Labour: whether staff can be trained to run the control system, not just start a motor. Raw material: whether the component supply is reliable enough to keep a formula on specification week to week.
  • What the Kazakhstan Project Shows About Each: This project is instructive precisely because none of the four was ideal. Raw material came in as wheat with barley held back for routine production, so the formula runs on what is actually available. The site side carried the steelwork and cabling. The weather delayed intake through the outdoor silos.

What the Line Has to Work With: Material, Interfaces and Site Conditions

A mash feed production line is designed against the conditions it will actually meet, not against a catalogue. Three of those conditions shaped this project.

Raw material intake area and wheat receiving pit feeding the mash feed production line
Raw Material Intake And Wheat Pit
Outdoor silo connected to the bucket elevator that feeds raw material into the plant
Outdoor Silo And Elevator Connection

A Wheat-Based Raw Material Basis

  • Wheat as the Primary Component: The line was built around wheat as the main raw material. Barley was held in reserve and intended for routine production rather than commissioning, where the normal mix runs at roughly 80% wheat and 20% barley. Additives are handled separately as a small-ingredient stream.
  • Why the Raw Material Sets the Grinding Load: A wheat-based formula puts most of the size-reduction work on the hammer mill, and the mill’s behaviour follows the raw material rather than the drawing. Impurities in the incoming grain reach the screens, and screen condition becomes a running cost rather than a design parameter.

Equipment Already On Site That the New Line Had to Tie Into

  • Interfaces, Not Standalone Machines: The new line was not installed on a clear site. Finished-feed bins, a bagging machine, a sealer and a bucket elevator were already present, and the new line had to hand material over to them. On this project the new scope added level indicators to the existing finished-feed bins rather than replacing them.
  • What the Interface Means for Selection: Existing equipment changes the selection problem. The discharge point, the transfer heights and the control handshake all have to match what is already standing, and an interface that is not checked before shipment becomes a site modification.

Site Constraints: Cold Weather and Outdoor Silos

  • Cold as a Material-Handling Constraint: Outdoor silos cannot be drawn down in the coldest part of the year, so raw material intake had to wait for the weather to turn. That is not an equipment fault and no controller fixes it — it is a scheduling constraint that has to be built into the project plan.
  • What It Implies for Line Configuration: A line that depends on outdoor storage needs its intake design to accept material in the windows when it can be delivered, rather than assuming a continuous feed. In this project the intake ran through the outdoor elevator into the indoor conveying run, and the first full trial followed once material could be moved.

Where the Batching Accuracy Comes From

Two numbers decide whether a mash feed production line holds its formula: how precisely the ingredients are weighed, and how evenly they are mixed afterwards. Both are stated in the specification for this line, and both were verified on site.

Batching bins and the 1-tonne batching scale in the weighing area of the line
Batching Bin And Weighing Area
Control cabinet with PLC and HMI touchscreen running the batching recipes
Control Cabinet With HMI Touchscreen

The 1-T Batching Scale: Static ≤1‰ and Dynamic ≤3‰

  • Two Accuracies, Not One: The batching scale on this line is rated at static ≤1‰ and dynamic ≤3‰. The gap between the two figures is the whole engineering problem. A static reading can be taken with the system at rest and the load settled. A dynamic reading has to be correct while material is still moving into and out of the weighing hopper, which is the condition the scale actually works in.
  • What Makes the Dynamic Figure Holdable: Holding the dynamic figure needs a load cell installation that is protected from mechanical disturbance, a discharge arrangement that does not shock the hopper, and a control sequence that allows settling before the weight is captured. This line uses a double-gate arrangement on the weighing hopper specifically so that discharge is controlled rather than dumped.

Mixing Uniformity at 97.7 Percent

  • What the Number Describes: Mixing uniformity of 97.7% describes how evenly a marker component is distributed through a batch after mixing. For a mash feed it is the difference between an animal receiving the intended ration and receiving a ration that happens to be high or low in one additive.
  • What Delivers It: This line uses a single-shaft ribbon mixer at 15 kW with a double-layer rotor, which increases the convective and shear action inside the trough. Both the mixing time and the discharge gate opening are adjustable at the control panel, so the mixing cycle can be matched to the formula rather than fixed at a factory default.

Commissioning Reality: 22 Working Days on Site

The on-site phase ran from 8 to 29 January 2026 and closed in 22 working days, with an engineer and a technician on the supplier side alongside a four-person construction team. The record is worth reading in full because the line did not go from wiring to production in one continuous run.

Engineer completing control wiring and terminal connections during commissioning
On-Site Wiring And Termination
Hammer mill used in the grinding section of the mash feed production line
Hammer Mill Grinding Section
Bucket elevator and screw conveyor transferring material between process stages
Bucket Elevator And Conveyor Link

From Wiring and Power-On to First Material Through the Line

  • The Sequence: Work opened with a full inspection of installed equipment, focused on connection angles and flexible joints, and a consolidated defect list issued to the site team. Cabling followed, then power-on, then motor testing across the feed line, level indicators and control circuits. Weighing calibration with check weights and pneumatic valve testing came next.
  • First Material: The first full trial followed once the raw material arrived. Material moved from the outdoor silo through the conveying run to the bin above the mixer without intervention, which confirmed the mechanical path. Minor leakage appeared at joints where sealing was incomplete, and was corrected the following day before the trial continued.
  • Eight Tonnes Through the Mill: Over the following two days the grinding stage ran through approximately eight tonnes of wheat, which emptied the outdoor silo and gave the first sustained view of mill behaviour under production load.

Grinding Section in Production: Current Stability and Screen Wear

  • The Current Problem and Its Cause: Under production load the ammeter on the hammer mill fluctuated across a wide band, with the variable-frequency drive sitting between 5 and 7. The cause was uneven feed into the mill rather than the mill itself: an uneven feed rate makes the load swing regardless of how the drive is set.
  • The Setting That Held: Once the feed was evened out, the drive could be run up to 14 with a stable current reading. Above 14 the reading began to fluctuate again, so 14 became the working setting for this raw material.
  • Screen Wear as a Running Cost: Screens were replaced four times over two days. The cause was reported plainly: the incoming grain carried a relatively high level of stone and foreign matter, which strikes the screen during grinding. Two responses followed — the site was advised to hold spare screens, and a technical recommendation was made to add a cleaning sieve below the magnetic separator on the intake, so that foreign matter is removed before it reaches the mill.

Training, Documentation and What the Operator Can Do Alone

Commissioning closed with operator training running alongside the trial production, and the training record is more informative than a completion certificate because it distinguishes between sections.

Operators receiving on-site training on the control system at handover
Operator Training On Site

Two-Language Manuals: Chinese and Russian

  • What the Manual Covers: Operation manuals were supplied in both Chinese and Russian. They run beyond a component list: each item of equipment is described by function, start-up procedures are written in reverse material-flow order, and the control interface is documented item by item, including the administrator access, the parameter and recipe menus, and the check-weight calibration procedure for the batching scale.
  • Why Reverse-Order Start-Up Matters: Starting in reverse material flow order — discharge end first, feed end last — is the difference between a line that fills and a line that blocks. Written down in the order the operator presses buttons, it transfers as a procedure rather than as a habit picked up on site.

Handover Gap: Grinding Section vs Batching Section

  • What the Operators Could Do Independently: By the final day of training, operators were starting and stopping the line themselves and were assessed as broadly competent on the grinding section.
  • What a Handover Plan Should Assume: The practical lesson for anyone planning a similar project is that training time should be budgeted by section, not by day. The grinding section can be signed off quickly; the batching section should be expected to need a second pass, and a return session should be planned for rather than improvised.

Planning a mash feed production line for your own capacity target? Send us your raw material, target output per day and site power supply and we will return a line configuration for review.

  • What size mash feed production line is needed for 10 TPD?
  • Capacity is set by the grinding and mixing stages rather than the packing stage. In this project the 10 TPD output is carried by a hammer mill rated at 160/200 kW and a 15 kW single-shaft ribbon mixer, with the remaining equipment sized to keep material moving between them.
  • How accurate is automatic batching on a mash feed production line?
  • This line’s batching scale is rated at static ≤1‰ and dynamic ≤3‰. The dynamic figure is the one that matters in production, because it applies while material is still moving. Holding it depends on protecting the load cell installation from mechanical disturbance and allowing the weight to settle before it is captured.
  • What raw materials can a mash feed production line handle?
  • This line was built around wheat as the main component with barley in reserve, at a routine mix of roughly 80% wheat and 20% barley, plus a separate small-ingredient stream for additives. Grinding behaviour follows the raw material, so grain cleanliness directly affects screen life and throughput.
  • What has to be prepared on site before the line is installed?
  • The site side carries the civil and structural work and the main power cable, together with supports, piping and access steelwork. Power capacity has to cover both the installed load and the starting current of the largest motor, and the intake needs a workable path for raw material delivery and storage.
  • How long does commissioning take for a 10 TPD mash feed production line?
  • The on-site phase for this line ran 22 working days, including cabling, power-on, motor testing, weighing calibration, first material through the line and operator training. Weather, raw material availability and the readiness of the site’s own contractors all move that number more than the equipment itself does.
  • Why do hammer mill screens wear out quickly in feed production?
  • Screens wear when the incoming grain carries stone and foreign matter, because those particles strike the screen during grinding. In this project four screens were replaced over two days on raw material described as high in impurities. Fitting a cleaning sieve ahead of the mill on the intake side removes that material before it reaches the screens.
  • What training and documentation come with the feed production equipment?
  • This project was handed over with operator training running alongside trial production, plus operation manuals in Chinese and Russian covering equipment function, reverse-order start-up procedures and the control interface item by item, including batching scale calibration with check weights.

Hot Sale

Successful Cases

BEFORE YOU SEND INQUIRY

We kindly ask you to provide the following details to help us offer the most suitable solution promptly:

Your detailed input is greatly appreciated!

Get in touch Now!

Your privacy is important to us and your information will be well protected!

Boot a Zoom Meeting Now!

Get Your Customized Farming Solution

Offering customized one-stop animal farming project & technology solutions. Please fill out the following information so that we can provide you with a tailored solution: